Case Studies

Explore real case studies of blocked drain solutions in Brisbane, Ipswich & Gold Coast—see how SEQ uses CCTV, jetting & relining to fix issues fast.

Case Study: Emergency Sewer Relining for a Yatala Logistics Hub

Project Snapshot

  • Client: 24/7 Distribution Centre in Yatala, QLD

  • Problem: Collapsed sewer main causing health‑code breach notices

  • Pipe Details: 150 mm asbestos‑cement pipe, 48 m run beneath warehouse floor

  • Response Time: 2 hours onsite, full restoration in 6 hours

  • Technologies Deployed: CCTV crawler, high‑pressure jetting, sectional pipe bursting, UV‑cured CIPP liner


1. The Challenge

1.1 Symptoms Reported

  • Overflow from floor gullies near cold‑storage area

  • Sewage odour infiltrating packing line

  • Two forklifts forced offline due to spill contamination

1.2 Root‑Cause Investigation

Sequential camera passes revealed:

  1. Pipe Collapse: 60 % cross‑section loss at 31 m mark.

  2. Offset Joints: Five joints with ≥5 mm vertical displacement.

  3. Grease Build‑up: 8 mm layer on pipe walls due to in‑house canteen discharge.

“Shutting the loading bay even for half a day would cost tens of thousands in missed dispatch targets, so trenchless was non‑negotiable.”
— Operations Manager, SEQ Blocked Drains


2. Solution Delivered

Step‑by‑Step Remediation

  1. Flow Diversion – Deployed temporary above‑ground transfer pump to keep kitchens operational.

  2. High‑Pressure Jetting – 9 mm spinner nozzle at 5 000 PSI cut through grease and debris.

  3. Sectional Pipe Bursting – Replaced 4 m collapsed segment with 160 mm HD‑PE SDR 17 pipe.

  4. UV‑Cured CIPP Lining – Pulled‑in‑place liner installed across remaining 44 m; UV light train cured in 8 minutes.

  5. Final CCTV Verification – Confirmed smooth bore and grade compliance (<1 % deviation).

2.1 Equipment & Materials

Equipment / Material Purpose Key Specification
CCTV Crawler Locate collapse & offsets 30 m push rod, self‑level camera
Jetting Unit Remove grease & debris 5 000 PSI, 80 L/min
Pipe Bursting Rig Replace collapsed section 35 kN pulling force
HD‑PE Pipe New carrier pipe 160 mm OD, 50‑year design life
UV‑CIPP Liner Restore remaining run 4 mm wall, styrene‑free resin